Rooppur nuclear plant begins second trial supply to the national grid

Date: 2026-11-23
news-banner
The first unit of the Rooppur Nuclear Power Plant began supplying electricity to Bangladesh's national grid on a trial basis for the second time on Monday, 23 November, at 10:20am. The plant is not entering commercial production. The supply is intended for technical tests, Prothom Alo and The Daily Star reported.

Project Director Dr Md Kabir Hossain told Prothom Alo that about 300 to 350 megawatts would be supplied for 10 to 24 hours. In a press release cited by The Daily Star, he said engineers would assess the plant's generation system and its integrated operation with the grid, including the turbine, generator, control systems and connecting equipment.

The first trial began at 3:16pm on Tuesday, 17 November, when the unit started supplying 350 megawatts. The output was later reduced to 300 megawatts. After 8 hours and 34 minutes of continuous supply, the plant was disconnected for further technical evaluations, Prothom Alo reported. The Daily Star said the unit was taken off the grid after more than eight hours.

Plant sources said the trial follows International Atomic Energy Agency guidelines and is meant to raise generation capacity in stages. During the tests, Unit-1 may be temporarily shut down and output may be raised or lowered. After the current trial, the plant is expected to be disconnected for further checks. Electricity supplied during the tests can be used by consumers, but an uninterrupted or stable supply is not yet guaranteed. Power Grid Bangladesh PLC will work to keep the grid in balance, and Bangladesh Power Development Board officials will monitor the supply, according to Prothom Alo and The Daily Star.

Raising the unit gradually to full capacity will require licences and approvals from the Bangladesh Atomic Energy Regulatory Authority (BAERA), which will first receive the test results. Officials said that process may take several months. Under the contract with the Russian contractor, commercial supply at full capacity from the first unit is due after 10 months of trial operation, Prothom Alo reported. Plant officials said Bangladesh had become the world's 33rd nuclear electricity-producing country, though formal recognition would come after full-scale supply begins.

Rooppur is the country's largest single project. It is being implemented by the Bangladesh Atomic Energy Commission under the Ministry of Science and Technology, while the state-owned Nuclear Power Plant Company Bangladesh Limited (NPCBL) handles operations. Russia's Atomstroyexport is building two units of 1,200 megawatts each. The project's deadline, originally December 2025, has been extended twice to June 2028. The estimated cost now stands at Tk 138,686 crore, about Tk 26,000 crore higher because of the rise in the dollar, Prothom Alo reported. The Daily Observer and Dhaka Tribune have previously published the same figures.

Source: Prothom Alo, The Daily Star, The Daily Observer, Dhaka Tribune